Service 03

Utility trenching in Arizona, any size trench

Site lighting, electrical, communications or any other underground installation. We have the equipment and the experience to open the trench your drawings call for and keep your schedule on track.

In short

Utility trenching is the open-cut excavation of a narrow, continuous trench so conduit, cable or pipe can be placed below grade, then bedded, backfilled and covered. Premier Underground trenches for electrical, communications and site lighting across Arizona, in any size, and handles the cutting, hauling and restoration around the trench.

01 — What it is

When do you need a trenching contractor?

You need one whenever power or communications has to get from one point to another below the surface and the route can be opened from above.

Open trench is the most direct way to put dry utilities in the ground. The whole route is visible, the conduit can be laid, spaced and inspected before it is covered, and the trench can be sized for one conduit or for several systems stacked in layers.

It is also where an underground schedule is won or lost. A trench that is the wrong width, off line, or left open waiting on another trade holds up everyone behind it. That is why electrical contractors, general contractors, developers and renewable energy contractors hand the trench to a crew that does nothing else.

Typical reasons customers call us:

  • Primary and secondary electrical feeds to a new building or campus
  • Communications and fiber conduit, including relocations
  • Site lighting and camera circuits across parking lots and roadways
  • Direct-buried DC and AC collection on solar sites
  • Any trench that is part of a larger turnkey dry utility package
Backhoe digging a narrow utility trench along a saw-cut road edge beside curb and gutter, with traffic delineators in place
A narrow trench along a saw-cut road edge, with traffic control in place.

02 — Trench types

What kind of trench does your job need?

The utility decides the trench. Width, depth, bedding and backfill all follow from what is going in and whose specification governs it. These are the trenches we are asked for most.

TrenchUsed forWhat usually goes with it
Narrow utility trenchSite lighting, camera circuits and single communications or electrical conduit runsPole-base augering on lighting and camera work
Joint trenchSeveral dry utilities sharing one excavation, each at its own level and separationConduit, vaults and pull boxes under a dry utility scope
Duct bank trenchMulti-row banks of conduit for medium-voltage, low-voltage and communications feedersDuct bank and conduit installation, encased or direct-buried
Wide layered trenchDirect-buried systems installed in layers, such as DC, AC, fiber optics and grounding on a solar siteBedding and shading material placed between each layer
Trench through pavementRoutes that cross sidewalk, curb, asphalt or a building slabSaw-cutting and removal first, surface restoration last
Trench in rockRoutes through caliche, rock and other ground a bucket will not digHard dig and rock trenching equipment

Not sure which applies? Send the drawings. The utility provider's or engineer's specification usually answers it, and our estimators read those every day.

03 — Scope

What is included in a Premier trench.

As much or as little as you want. We can hand you an open trench ready for your electricians, or carry everything from the first cut to the finished surface.

  • Layout of the route from your drawings
  • Saw-cutting and removal of pavement, sidewalk or slab over the route, indoors or outdoors
  • Trench excavation to the width and depth the installation calls for
  • Hammers and rock trenchers where the ground is hard
  • Trench protection and safe access once depth calls for it
  • Bedding and shading material, placed in layers where the design stacks systems
  • Conduit and duct bank installation, when it is part of our scope
  • Backfill, and spoils haul-off in our own dump trucks
  • Sidewalk, curb and asphalt returned to original condition, coordinated for you
Long straight open trench holding a multi-row bank of PVC conduit on spacers, with orange barrier fence alongside on a desert site
A straight trench, a conduit bank on spacers and barrier fence along the open edge.

04 — Method

How we run a trenching job.

Trenching looks simple from the road. Keeping a long trench safe, on line and moving every day takes a routine, and ours is the same on a one-day service call as on a data center.

  1. Preconstruction

    Price the real trench

    Our estimators work from your drawings and specifications and price the full scope, including hard ground, haul-off and restoration, so the number holds up in the field.

  2. Hand-off

    Carry your requirements across

    Your requests, schedule and needs are written into the contract and handed from preconstruction to the project manager who will run the job.

  3. Operations

    Line up material, equipment and crew

    Material is procured ahead of need. Equipment, tools and people are scheduled so the right resources reach the right task at the right time.

  4. Every day

    Plan, then dig

    Each day starts with a job safety analysis and an operations meeting. Field leadership completes a trench inspection daily, and all of it is recorded digitally.

  5. Fleet

    Keep the iron working

    In-house mechanics look after our equipment and vehicles, so a breakdown does not turn into a hole in your schedule.

  6. Quality

    Check before it is covered

    Quality control visits the site while there is still time to adjust direction, then walks the finished work with operations at close-out.

Our rules around an open trench: 3, 4, 5, 6

Spoil stays 3 feet back from the edge. A safe way in and out at 4 feet. Trench protection at 5 feet. Fall protection at 6 feet. These are Premier's core rules on every job, every day, whatever the size of the project. Read more about our safety program.

05 — Proof

Trenching projects, from solar fields to a hospital campus.

Three jobs where the trench was the scope, and where the ground, the specification or the neighbors made it harder than a line on a drawing.

All project experience

Solar · Renewable energy

Mohave Solar

McCarthy Building Corp.

  • 10,000+Linear feet of trench
  • 24 in–9 ftTrench widths
  • 3,200+Yards of bedding and shading
  • 10.9 MWGeneration system

Trenching for direct-buried DC and AC. We placed multiple layers of bedding and shading so DC, AC, fiber optics and grounding could each be installed at their own level.

Military · Luke Air Force Base

Luke AFB F-35

B & D Industries

  • 3Systems trenched: primary, secondary, low voltage
  • USACESpecifications coordinated

Trenching for underground power distribution, followed by medium-voltage and service raceways and communications conduit. The work was coordinated with the Corps of Engineers and the local utility providers.

Healthcare · Arizona

Banner Behavioral Health

Delta Diversified / Oakland

  • 2New feeds: primary and secondary
  • APSUtility provider specification

Trenching for a new primary and secondary feed through a highly congested area with critical paths. All underground conduit systems were installed to the specification of the utility provider, Arizona Public Service.

06 — Quick answers

Trenching questions we hear before a bid.

What size trench can Premier Underground dig?

Any size the installation calls for. We dig narrow trenches for site lighting and communications, and wide ones for stacked or side-by-side systems. On the Mohave Solar project our trenches ranged from 24 inches up to 9 feet wide.

Do you only dig the trench, or do you install the conduit too?

Either. Some customers want an open trench ready for their own electricians. Others hand us the whole underground scope: trench, conduit or duct bank, bedding, backfill and restoration. Tell us where you want the line drawn and we will price it that way.

What happens when the trench runs into rock or caliche?

We bring in the hard dig equipment. Premier Underground runs backhoe hammers, excavator hammers and rock trenchers, so hard ground changes the method, not the contractor. Share any soils information you have when you request a quote so the estimate reflects the real ground.

Can you trench across a road or driveway that has to stay open?

When open cut is not possible, we use horizontal directional drilling to install the pipe or conduit under the crossing instead. Many jobs combine the two: open trench where the ground is clear, and a bore under each road or driveway.

Where in Arizona do you provide trenching?

Statewide. Premier Underground is headquartered in Avondale, in the Phoenix metro area, and takes on trenching work across Arizona.

Your job. Your way.

Got a trench to dig?

Send the drawings and the schedule. Our estimators will price the trench you actually need, including the hard ground, the haul-off and the patch-back.

Premier Underground Construction, LLC
575 N Eliseo Felix Jr Way, Avondale, AZ 85323
623-748-9650 · estimating@premierunderground.com
Serving all of Arizona since 2004