Project experience

Underground utility projects, measured in feet

Nine jobs from our project history, each with the contractor we worked for and the quantities that went in the ground. Data halls, an airport people-mover, a solar field, a hospital feed and a downtown basement.

Four numbers from four jobs

  • 28,975ft4-inch duct bank installed on Zayo Dallas DC 01
  • 10,000+ ftTrench for DC and AC cable at Mohave Solar
  • 405-inch conduits run 18 feet deep at Block 23
  • 16+Manholes on the PHX Sky Train segment

How to read this page

What kind of projects does Premier Underground build?

We build the underground power and communications scope on projects where a missed date or a damaged line is expensive. On every job below we worked as the underground subcontractor. Each card names the electrical contractor and the general contractor we worked for, where the record lists both, and gives the quantities from our own project records.

The coloured edge on each card shows the utility: red for electric, orange for communications, and both where the job carried power and communications together.

A note on this list

This is representative experience from our project history, not a list of everything we have built or of work under way today. Current references by sector are available on request. Request a quote and tell us which sector you need.

01 — Mission critical

Data center projects

Both of these ran on accelerated schedules. Both were measured in thousands of feet of conduit and thousands of yards of concrete or backfill.

Underground work for data centers

Mission critical · Accelerated schedule

Iron Mountain Data Center

Sturgeon Electric / Holder Construction

  • 2,500+Ft of hard dig, power
  • 4,100Ft of hard dig, comms
  • 244-inch conduit configuration
  • 4,000+Cu yd ready-mix backfill

More than 2,500 feet of hard dig for medium- and low-voltage conduit, and 4,100 feet of hard dig for communications in a twenty-four-way bank of 4-inch conduit. The runs were backfilled with more than 4,000 cubic yards of ready-mix.

Mission critical · Accelerated schedule

Zayo Dallas DC 01

JDCM

  • 28,975Ft of 4-inch duct bank
  • 4,450Ft of 2-inch duct bank
  • 15,650+Ft of 1-inch Sch 40 for controls
  • 1,080Yd of concrete and slurry

1,940 feet of excavation and trench carrying 28,975 feet of 4-inch duct bank, 4,450 feet of 2-inch duct bank and more than 15,650 feet of 1-inch Schedule 40 conduit for controls, finished with just over 1,080 yards of concrete and slurry.

Related services: duct bank and conduit installation, hard dig and rock trenching, excavation.

02 — Aviation

PHX Sky Train at Phoenix Sky Harbor

Two scopes for the airport's automated train: the raceways that power one segment, and the fiber that had to move before the next phase could be built.

Underground work for airports

Aviation · Critical underground infrastructure

PHX Sky Train

DP Electric / McCarthy-Hunt JV

  • 145-inch encased conduits
  • 44-inch encased conduits
  • 16+Manholes
  • T4 → T3Segment completed

Excavation and installation of the power, propulsion and low-voltage raceways for the segment from Terminal 4 to Terminal 3. The system is fourteen 5-inch and four 4-inch conduits encased in rebar and concrete, with more than sixteen manholes.

Aviation · Fiber relocation

PHX Sky Train Phase 2 fiber relocate

Wilson Electric / Hensel Phelps

  • 5,400+Ft of fiber rerouted
  • City of PhoenixFiber owner

In preparation for Sky Train Phase 2, more than 5,400 feet of City of Phoenix fiber had to be rerouted to clear the way for construction of the train to the rental car facility.

Related services: encased duct bank, manhole and vault excavation, vacuum excavation.

03 — Commercial & mixed-use

Downtown and hospitality projects

One job with no room and two weeks to finish. One with a full site of medium-voltage and low-voltage raceways.

Underground work for commercial projects

Mixed-use · Downtown Phoenix · Accelerated schedule

Block 23

Delta Diversified Enterprises / Whiting-Turner

  • 405-inch conduits
  • 18 ftDepth of run
  • 2 wksSchedule
  • 2Basements connected

The new building needed power from the existing Block 22 building, and the schedule was two weeks. We ran forty 5-inch conduits from the Block 22 basements to the new Block 23 basements at a depth of eighteen feet, in downtown Phoenix conditions.

Hospitality · Underground critical infrastructure

West Valley Casino, Phase 1

Delta Diversified / Hunt-Penta JV

  • MVMedium-voltage raceways
  • AllElectric and low-voltage dry utilities

We provided the medium-voltage underground raceways and all electric and low-voltage underground dry utilities. This phase was built to serve as the temporary casino.

Precast concrete vault with two manhole frames set inside a green steel trench shield
Our work: a precast vault set inside a trench shield.

Deep runs next to existing buildings call for protective systems and a plan for where the spoil goes. Our rule is trench protection at five feet, on every job. Read about the 3-4-5-6 rules and our safety program.

Related services: turnkey dry utility construction, saw-cutting and demolition, restoration.

04 — Healthcare & federal

Projects built to someone else's specification

On these two the measure was not footage. It was whether the installation met the utility's and the agency's requirements the first time.

Healthcare · Critical underground infrastructure

Banner Behavioral Health

Delta Diversified / Oakland

  • APSUtility provider
  • 2New feeds: primary and secondary

Working in conjunction with APS (Arizona Public Service), we trenched for a new primary and secondary feed through a highly congested area with critical paths, and installed all underground conduit systems to the utility's specification.

Federal · Underground power distribution

Luke AFB F-35

B & D Industries

  • 3Systems trenched: primary, secondary, low voltage
  • USACECorps of Engineers coordination

Trenching for primary, secondary and low-voltage infrastructure. We installed medium-voltage and service raceways and finished with communications conduit, working with the Corps of Engineers and the local utility providers so every specification was met.

Related services: trenching, conduit installation, horizontal directional drilling.

05 — Solar & renewables

Utility-scale solar project

Direct-buried cable in layers: DC, AC, fiber optics and grounding, each on its own lift of bedding and shading.

Direct-buried means the cable sits in the trench without conduit. What protects it is the material around it, so the bedding below and the shading above each layer are placed with as much care as the cable. At Mohave Solar that came to more than 3,200 yards of material.

Underground work for solar and renewables

Related services: trenching, rock trenching, haul-off.

Solar · Sensitive underground infrastructure

Mohave Solar

McCarthy Building Corp.

  • 10,000+Linear ft of trench
  • 24 in – 9 ftTrench width
  • 3,200+Yd of bedding and shading
  • 10.9 MWGeneration system

More than 10,000 linear feet of trench for direct-buried DC and AC installation, from 24 inches up to 9 feet wide. Multiple layers of shading and bedding carried DC, AC, fiber optics and grounding for a 10.9 megawatt generation system.

06 — Summary

All nine projects at a glance

The same list in one table, for the estimator who wants to scan it.

ProjectSectorWorked forScheduleOur scope
Iron Mountain Data CenterData centerSturgeon Electric / Holder ConstructionAcceleratedHard dig for power and communications conduit, ready-mix backfill
Zayo Dallas DC 01Data centerJDCMAcceleratedExcavation, trench, duct bank, controls conduit, concrete and slurry
PHX Sky TrainAviationDP Electric / McCarthy-Hunt JVNormalEncased power, propulsion and low-voltage raceways, manholes
PHX Sky Train Phase 2 fiber relocateAviation, telecomWilson Electric / Hensel PhelpsNormalRerouting City of Phoenix fiber
Block 23Mixed-useDelta Diversified Enterprises / Whiting-TurnerAcceleratedForty 5-inch conduits between basements at 18 feet
West Valley Casino, Phase 1HospitalityDelta Diversified / Hunt-Penta JVNormalMedium-voltage raceways, electric and low-voltage dry utilities
Banner Behavioral HealthHealthcareDelta Diversified / OaklandNormalTrench and conduit for new primary and secondary feed, with APS
Luke AFB F-35FederalB & D IndustriesNormalTrench, medium-voltage and service raceways, communications conduit
Mohave SolarSolarMcCarthy Building Corp.NormalTrench, bedding and shading for direct-buried DC, AC, fiber and grounding

07 — In the field

What our work looks like

These photos show Premier crews and equipment on our jobsites. They are not pictures of the named projects above.

Premier crew in hard hats and hi-vis vests setting banks of grey PVC conduit in a sloped open excavation
Long straight open trench with a multi-row bank of PVC conduit on spacers and orange barrier fence alongside
Tracked chain rock trencher loaded on a lowboy trailer behind a Premier tractor
Excavator loading soil into a Premier Underground dump truck
PVC conduit duct bank sweeping up into an organized rack of stub-ups inside a steel-framed building

Your job. Your way.

Have a project like one of these?

Send the drawings and tell us the schedule. We will price the real scope, including the hard dig and the restoration.